Why this page exists
Sumerian Oil & Gas Inc., formerly Cleo Energy Corp., was acquired out of receivership in November 2025 through a court-approved Reverse Vesting Order. The Alberta Energy Regulator did not oppose the acquisition. Eleven months later the company's sites are in the custody of the Orphan Well Association by order of the AER, its production is shut in, and the abandonment program the AER itself ordered has been stood down.
The company will appeal the October 5, 2026 order within the 30-day appeal period and has asked the Minister of Energy and Minerals to review the AER's conduct on this file. This page is the record on which both of those requests rest. It is drawn from the AER's own orders, letters and emails, the company's submissions, and the court file. Where the AER's account and the company's differ, both are stated. The documents are listed below and are available on request.
What the AER knew before the acquisition
By 2025 Cleo Energy Corp. was in receivership. Its AER record included a pipeline release on licence P58349 in April 2025, suspected cause internal corrosion, on a segment where the AER's own inspections had flagged a corrosion monitoring deficiency as High Risk in March 2018; a second pipeline incident on P54028; twelve open field inspections, five of them on licences that actually belonged to another operator but still showed under Cleo in the AER's system; fifteen wells past their mineral-lease-expiry abandonment deadlines; packer isolation tests for 2025 not done; no audited financial statements for 2023 or 2024; no current pipeline operations manual; and a corporate emergency response plan dated 2017 in places. In February 2019 the AER had assessed Cleo as "managing their pipeline infrastructure well."
On September 19, 2025, two months before closing, the AER wrote to the incoming ownership and set out what the company would carry forward: the closure spend quota history, the orphan levy and administration fee history including 2025 penalties, the expired-lease wells and the open inspection files. The AER later described that letter as "a good summary of what Sumerian should expect." The Reverse Vesting Order was granted by the Court of King's Bench on November 14, 2025 with the AER as a party with notice. On November 24 the AER confirmed Sumerian as licensee.
Every deficiency now being enforced existed on that date, and the regulator had listed it in writing.
What the company did
In the nine months after closing Sumerian rebuilt the compliance program from the ground up and reported its progress to the AER in writing every month from March to August 2026, answering each AER comment item by item.
The AER inspected these assets 31 times in Sumerian's first nine months. It had inspected Cleo 29 times in the two years before the acquisition.
The company's engagement with the AER
Sumerian did not wait for the AER to come to it. The record shows the company in continuous contact with the regulator from the first weeks of ownership.
Through all of this the company asked the AER, in writing and more than once, for a licence-level calculation of the security and levy amounts and of the well count it was being held to. The AER has acknowledged that pipeline segments transferred to another operator still show under Sumerian in its systems, that three segments it had counted were never constructed, and that at least one inspection was closed because the noncompliance was Cleo's. In June 2026 the AER itself contacted Fire Creek Resources about transferring a licence that still showed under Sumerian; it did not contact Sumerian. The AER knew the assessed asset base was wrong, acted on that knowledge with the other operator, and continued to enforce the amounts against Sumerian. It has never produced the reconciliation.
What the AER did
The AER's response to that engagement was five orders and two environmental protection orders between April 22 and October 5, 2026, three of them shut-ins, and then the order transferring care of the company's sites to the Orphan Well Association.
June 19. The AER suspended the Shorncliffe field on the ground that the site-specific emergency response plan was inadequate. The plan was Cleo's 2017 document, in the AER's own files, which Sumerian was rewriting against Directive 071; the AER had brought the new edition into force on February 2, 2026 and given existing operations until their next scheduled 12-month update to comply. No release, injury or complaint had occurred. On June 20 the Court of King's Bench granted an interim injunction. On June 22 Sumerian submitted calculations on the AER's own AERH2S model showing the field did not require a site-specific plan at all. On June 23 the Director wrote that "a operations specific ERP is no longer required" and that he "no longer see[s] the need for the June 19, 2026, suspension order," and rescinded it. On June 24 the AER rescinded the related audit notices "as the Shorncliffe Operation-specific ERP was determined to not be required." Seven days later it issued its next notice of possible suspension.
July 20. On June 2 the AER had accepted payment of the $445,368.77 security in instalments; on June 18 it withdrew that. On July 15, after a pre-issuance meeting, it set new terms in writing: $340,195.24 by cheque, and a payment plan for the balance would follow. On July 17 it invited further information by 2:00 pm on July 20. At 9:03 am on July 20 a cheque for $340,195.24 was delivered to the AER's mail room with a cover letter. The cheque was dated July 23. At 3:40 pm the Director wrote that because the cheque was post-dated the AER could not tell whether the fees were paid, and refused the payment plan because Sumerian "has not followed through on previous commitments." At 3:41 pm the AER served an order shutting in every well, facility and pipeline the company operated within 14 days. The Order identified no safety or environmental risk. Fourteen days was the time allowed to shut in infrastructure on CFB Wainwright, where civilian access is limited to set days. The company does not dispute that the cheque was post-dated, or that it stopped the cheque after the Order shut in the revenue that was to fund it. It disputes that a three-day post-date on a cheque for the full amount, delivered inside the AER's own window, was a reason to shut in a company's entire production rather than to say so and wait three days.
August 17. On August 15 a produced-water release occurred on pipeline P58349. Sumerian isolated the segment within about an hour, reported it to the AER and began cleanup. On August 17 AER inspectors attended and the entire Shorncliffe field was shut in. The same day the AER confirmed the corporate emergency plan compliant with Directive 071 and closed a pipeline inspection on P54028 as Low Risk. The other release sites under AER order date from the prior operation; the AER's own inspection reports record the releases at 15-35-021-07W4 from an April 30 inspection without dating them, and P58349 had a prior release under Cleo on the same line in April 2025.
September 21. A further order, holding the company to the prior operation's defaults: packer tests for the 2025 calendar year, when Sumerian held the licences for seven weeks; decommissioning reports for 2023 and 2024; a reclamation plan from March 2024. The same order states that the AER has "limited operational and financial history" for Sumerian.
October 5. At 8:56 am on Friday October 2 the AER requested a meeting that morning on an order placing the company's sites under the Orphan Well Association, and said that without a response by noon the decision would be made on the information in hand. The meeting was held on Monday October 5. Sumerian opposed the order and advised the AER of the $2 million financing it would end. The order was signed and served the same day. The company's emergency line was rerouted to the OWA; the company must obtain the OWA's written approval to enter its own sites. On October 9 the order was amended because its licence list was incomplete. The liability the AER is moving onto the industry-funded Orphan Well Association is, on the AER's own estimate, $25 million or more.
October 17. A fire began on the CFB Wainwright range. Wells Sumerian holds licences for were inside the fire area. At 7:15 pm the OWA advised that none of those wells had been shut in and that it did not plan to attend the base before October 27. At 7:48 pm the AER's on-call contact advised that the AER was not aware of the fire and that under the October 5 order there was nothing Sumerian could do.
The October 5 order required the OWA to shut in the wells within 14 days, the same period the AER's July 20 Order had given Sumerian. Sumerian argued before the Court of King's Bench, in June and again in July, that these wells, facilities and pipelines cannot be safely shut in within 14 days, and the AER's own staff acknowledged that it could not be done in that time. The Orphan Well Association, with the AER's full authority and no operator in its way, had not shut in a single well on the range twelve days into its 14-day period, and did not plan to attend until day 22. A fire then started on the range with the wells open.
What the AER will say, and the company's answer
The company's position
What the company is asking for
Before the acquisition
April 25, 2025
Cleo reports a pipeline release on P58349 at 01-22-040-08W4; suspected cause internal corrosion. The AER's inspection record traces the corrosion monitoring deficiency on that segment to March 2018
September 19, 2025
AER letter to the incoming ownership listing the obligations that will carry forward: closure spend quota history, orphan levy and fee history with 2025 penalties, 15 expired-lease wells past deadline, 12 open inspection files
November 14, 2025
Reverse Vesting Order granted, Court of King's Bench file 2501-09028. The AER has notice and does not oppose
November 21–24, 2025
Closing. A pipeline riser release is found on closing day. AER confirms Sumerian as licensee
Taking over
January 7, 2026
AER inspection finds no integrity management program on P54028
January 27
Notice of noncompliance: 2025 packer isolation tests, a Cleo-era obligation
February 2
AER's rewritten Directive 071 comes into force; existing operations have until their next scheduled 12-month update to comply
February 11
AER compliance summary letter; written response requested by February 26
March 10
Sumerian's CEO, CFO and COO meet AER Regulatory Compliance
March 24
AER notice of intent to take action; D013 noncompliant wells 142
March 25
Sumerian delivers baseline compliance workbook
The April Order
Date
Event
April 1
Closure quota security decision: $445,368.77 for the 2025 spend year, in which Sumerian held the licences for seven weeks
April 22
Order: RCAM plan, corporate ERP by May 8, pipeline integrity program by May 22, 27 expired-lease wells abandoned within 365 days, monthly reports. AER counts 115 D013 noncompliant wells
April 30
Inspection of F2927 at 15-35-021-07W4 records releases and staining; the report does not date them
May 6
Sumerian disputes the levy and security amounts in writing
May 21
Failure-to-comply letter
Instalments agreed, then withdrawn
June 1
Notice of possible suspension. Sumerian reports 142 to 97 wells and asks for seven instalments of $63,624.11
June 2
AER confirms in writing the security "may be made in the installments as requested"
June 9
AER confirms pre-acquisition levies "are not required to be paid due to the insolvency process"
June 17
AER meeting; Shorncliffe site plan submitted by the 3:00 pm deadline
June 18
AER says the plan "is from 2017," demands evidence by noon, withdraws the instalment arrangement
June 19
First shut-in: Shorncliffe field, on the emergency response plan. No release, injury or complaint had occurred
June 20
Court of King's Bench grants an interim injunction
June 22
Sumerian submits AERH2S calculations showing the field does not require a site-specific plan
June 23
AER Director: "a operations specific ERP is no longer required… I no longer see the need for the June 19, 2026, suspension order." Order rescinded
June 24
AER rescinds the related audit notices "as the Shorncliffe Operation-specific ERP was determined to not be required"
June 30
Second notice of possible suspension, seven days after the rescission
The July 20 Order
July 15
Pre-issuance meeting. AER sets terms in writing: $340,195.24 by cheque, then a payment plan
July 17
Revised draft order; further information invited by 2:00 pm July 20
July 20, 9:03 am
Cheque for $340,195.24 delivered, dated July 23
July 20, 3:40 pm
AER: cheque is post-dated, "unable to determine if the AER fees have been paid"; payment plan refused
July 20, 3:41 pm
Second shut-in: all wells, facilities and pipelines within 14 days. No safety or environmental risk identified
July 24
AER summary letter: interim financial statements required for the first time, within 7 and 11 days; AER's D013 count 95
July 27
Sumerian files regulatory appeal of the July 20 Order
July 31
Court stays the July 20 Order pending the appeal, conditional on $340,195.24 by August 5
August to October
August 4
Sumerian monthly update: D013 wells 142 to 73; 165 producing wells; 27 expired-lease wells costed at $1,159,200, rig ready
August 5–6
Court-ordered payment not made; stay lapses. AER restricts licence eligibility
August 13
AER response: 89 D013 wells on its count; further ten-day demands
August 15
Produced-water release on P58349. Segment isolated in about an hour, reported, cleanup begun
August 17
Third shut-in: AER inspectors attend and the entire Shorncliffe field is shut in. Same day, AER confirms corporate ERP "compliant with Directive 071"
August 18
Environmental Protection Order, F2927. Sumerian delivers its consolidated record letter
September 8
Second Environmental Protection Order, P58349
September 11
AER raises operational capacity and staffing
September 21
Order: packer tests in 7 days, integrity program in 30 and 90 days, open inspections in 30 days, financial statements. AER states it has "limited operational and financial history" for Sumerian
September 28
Court hearing; interim stay confirmed lifted as of August 6
October 2
AER requests a meeting the same morning on an order placing the sites under the Orphan Well Association
October 5
Pre-issuance meeting; Sumerian opposes. Order signed and served the same day. Emergency line rerouted to the OWA
October 9
Order amended; licence list "was incomplete"
October 16
Further failure-to-comply letter
October 17
Fire on the CFB Wainwright range. Sumerian notifies the OWA, the AER (Report 460044) and Range Control; OWA advises the wells on the range are not shut in and it does not plan to attend before October 27; at 8:12 pm the AER calls Sumerian for the Range Control number